The seller of a used ship says its ballast water management system (BWMS) was upgraded during the last yard stay. The file contains a service invoice, a type approval certificate and a commissioning report. Start by checking whether those documents describe the same version of the system now on board. Ask the technical manager or surveyor to confirm equipment identifiers and the control software version against the records.
Establish what changed on this ship
Build a short timeline by vessel IMO number. Start with the original installation, add the modification date and list the parts or software that changed. Request the manufacturer’s itemised change description and the service report showing what the technician installed. Tie each entry to a document number, date and revision. If the paperwork calls the work an “upgrade” without specifying its scope, ask the seller to identify the equipment and version before drawing a conclusion.
Next, ask which type approval applies to the system as modified. In its guidance for owners, DNV asks for the manufacturer’s declaration that the modified system still conforms to the existing Type Approval Certificate (TAC), or the new TAC that covers the modified design. Ask for the decision on the specific installation from the flag Administration or its authorised survey organisation, including the applicable survey and testing requirements. DNV guidance on installed BWMS modifications
Match each record to the installed system
| Request from the seller | What to reconcile |
|---|---|
| Manufacturer’s change list and service report | Match the work date, equipment identifiers and software version to the current installation. Ask the surveyor to verify unresolved differences on board. |
| Applicable TAC and ship-specific approval records | Identify the certificate and revision covering the modified configuration. Cross-check the approved ballast water management plan and relevant drawings or manuals where revised. |
| Survey and commissioning evidence | Ask which survey or test was required for this change and request the dated record showing the installed configuration covered and the outcome. Where a new International Ballast Water Management Certificate (IBWMC) was required, check the issued copy. |
| Record Book and recent system records | Compare recent recorded operations, alarms and service follow-up after the modification. Ask the technical manager to explain unresolved entries or gaps in the period covered. |
Under the IMO unified interpretation, an upgrade or change to a major component as defined in the BWMS Code is treated as a new installation, with commissioning testing and reissue of the IBWMC. For the individual ship, confirm whether its change falls under that provision and obtain evidence of the applicable survey outcome. The IMO survey guidelines also identify the plan, Record Book, type approval and equipment records as items for verification. IMO BWM.2/Circ.66/Rev.6, annex 1, section 3 · IMO Resolution A.1207(34), ballast water management survey guidelines
Worked example: a new filter assembly and an old commissioning report
In this fictional purchase, the 2023 commissioning report describes filter assembly A. A 2025 service report lists assembly B, and the seller supplies a photo of the current nameplate. Record that the recent service report and photo support the equipment change. The commissioning report supports the earlier configuration. Leave the 2025 acceptance entry open and ask for the manufacturer’s coverage statement or replacement TAC, the ship-specific decision on the change, and the survey or commissioning evidence that decision calls for.
A useful entry in the buyer’s open-items list is “2025 filter assembly B upgrade — survey outcome requested.” Add the service report reference, the named person responsible for obtaining the documents and the date the documents are needed for the purchase review.
If the purchaser plans to change flag, give the incoming Administration or its authorised organisation the same document set and ask what it requires for the vessel at transfer. Share the outstanding items with the pre-purchase surveyor so the onboard check targets the gaps found in the paperwork. For the wider purchase review, see the environmental compliance guide and the ship acquisition due diligence checklist.